Solution ID: prim35872 |
Why is the Resource Assignment’s duration not the same as the Activity’s duration? |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1 |
Problem: | Why is the Resource Assignment’s duration not the same as the Activity’s duration? |
Problem: | Why are the Activity’s Start and Finish date not the same as the Resource Assignment’s Start and Finish date? |
Problem: | Activity Dates and Resource dates don’t match. |
Cause: |
|
Cause: | In order to understand why this might happen, it is necessary to understand the rules by which Project Management decides whether the Activity’s duration should be pushed down to the Resource Assignment’s duration and vice versa: When an Activity’s Start and Finish are the same as a Resource Assignment’s start and finish, changes made to the Duration of the Activity are pushed down to the Resource Assignment Level. As long as the Start and Finish dates stay in sync, then changes made to the Activity’s Duration will be reflected in the Resource Assignment’s duration.
If the Drive Activity Dates option is switched on at the Resource Assignment level, then changes to the duration at the Resource Assignment level will also be pushed up to the Activity level.
If the Activity’s Start and Finish dates are not the same as the Resource Assignment’s Start and Finish dates, changes made to the Activity’s duration will not be pushed down to the Resource Assignment’s duration and changes made to the Resource Assignment’s duration will not be pushed up to the Activity’s Duration: If there is more than one Resource Assignment on an activity, then duration changes at the Activity Level will only be pushed down to those Resource Assignments whose Start and Finish dates match the Activity’s Start and Finish dates (and units will be allocated accordingly).
|
Fix: | The most likely reason why the Start and Finish dates of an Activity and its associated Resource Assignments may not be the same is that the Drive Activity Dates option has been switched off for a Resource Assignment and it’s Start Date, Finish Date or Duration have subsequently been changed manually. |
Fix: | Change your resources’ calendars to match the activity’s calendar and if there are multiple resource assignments, make sure that their calendars match each other’s. These calendars must match down to the exact workhours, because even if a resource is ending on the same day as the activity, if they are off by even 1 hour, then the resource assignment will no longer sync up with the Activity’s dates. |
Fix: | Make sure you have your Duration Type set to Fixed Duration and Units/Time or Fixed Duration and Units. |