prim15166:Help documentation for calculating ETC as remaining cost for activity is incorrect.

$
0
0
Solution ID: prim15166
Help documentation for calculating ETC as remaining cost for activity is incorrect.
Status: Reviewed
Version(s): 3.5, 3.5.1, 4.0, 4.0, 4.1, 4.1

Problem: Help documentation for calculating ETC as remaining cost for activity is incorrect.

From Project Management Help:



Technique for computing Estimate To Complete (ETC)


ETC = remaining cost for activity: Choose to calculate Estimate to Complete (ETC) values as the remaining cost to complete an activity (ETC = remaining duration of activity * applicable resource rates).

Fix:

This is a known problem in version 4.1 will be corrected in a future release.


When calculating ETC as remaining cost for activity, the calculation is:



ETC = remaining units of activity * applicable resource rates.