Solution ID: prim15166 |
Help documentation for calculating ETC as remaining cost for activity is incorrect. |
Status: Reviewed |
Version(s): 3.5, 3.5.1, 4.0, 4.0, 4.1, 4.1 |
Problem: | Help documentation for calculating ETC as remaining cost for activity is incorrect. From Project Management Help:
|
Fix: | This is a known problem in version 4.1 will be corrected in a future release. When calculating ETC as remaining cost for activity, the calculation is:
|