Solution ID: prim15039 |
Sample Global Change: Multiply budgeted labor units |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
Problem: | Sample Global Change: Multiply budgeted labor units |
Fix: |
Note: Changes could vary depending on Duration types. See: Solution #20011024135754: Duration Calculations for Project Manager/Project Management and Methodology Manager/Methodology Management |