Solution ID: prim15807 |
Earned Value Curve does not follow the Resource Curve |
Status: Reviewed |
Version(s): 4.1 |
From Primavera OCP
Problem: | Earned Value Curve does not follow the Resource Curve |
Fix: | This issue is an existing Enhancement Request. Please note that the Earned Value Option ‘Use Resource Curves’ in the ‘WBS’ view, ‘Earned Value’ tab does not actually use the resource curve (or the curve % complete) to calculate the Earned Value. This option simply overrides the Activity % Complete, and uses ‘Units % Complete’ for all activities where at least one resource assignment is using a resource curve. ‘Units % complete is distributed linearly across the duration of the activity. |