prim29559:Sample Report on Project Duration % Complete

$
0
0
Solution ID: prim29559
Sample Report on Project Duration % Complete
Status: Reviewed
Version(s): 4.0, 4.1, 5.0



Problem: Sample Report on Project Duration % Complete
Problem: Duration % Complete is not an available option when running a Project, WBS, or Project/EPS report.
Fix: To get a report on Project Duration % Complete, an Activities report will need to be run.  Then Group by Project and check the option to ‘Show summaries only’ if you don’t wish to see detail activity information.

A sample report is below:


5.x: Project Percent Complete5x.erp


4.x: Project Percent Complete4x.erp


Note: When running an Activities report, you need to have the project open that you want to run the report on. 