Solution ID: prim29559 |
Sample Report on Project Duration % Complete |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0 |
From Primavera OCP
Problem: | Sample Report on Project Duration % Complete |
Problem: | Duration % Complete is not an available option when running a Project, WBS, or Project/EPS report. |
Fix: | To get a report on Project Duration % Complete, an Activities report will need to be run. Then Group by Project and check the option to ‘Show summaries only’ if you don’t wish to see detail activity information. A sample report is below: 5.x: Project Percent Complete5x.erp 4.x: Project Percent Complete4x.erp Note: When running an Activities report, you need to have the project open that you want to run the report on. |