Solution ID: prim29718 |
Exporting Project Management / Project Manager project to P3 and activities with Remaining Duration = 1 come over with 0% and Remaining Duration = Original Duration. |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
From Primavera OCP
Problem: | Exporting Project Management / Project Manager project to P3 and activities with Remaining Duration = 1 come over with 0% and Remaining Duration = Original Duration. |
Problem: | When importing a P5 project into P3, remaining duration gets set to the original duration. |
Problem: | Percent complete coming into P3 as 0 when exporting from Project Management / Project Manager. |
Problem: | Activity percent complete changes when exporting from P6 and importing to P3. |
Cause: | If the activity’s RD = 1, this will occur. |
Fix: | This known problem in Project Management is currently under review and may be corrected in a future release. |
Fix: | Workaround:
|