prim29718:Exporting Project Management / Project Manager project to P3 and activities with Remaining Duration = 1 come over with 0% and Remaining Duration = Original Duration.

$
0
0
Solution ID: prim29718
Exporting Project Management / Project Manager project to P3 and activities with Remaining Duration = 1 come over with 0% and Remaining Duration = Original Duration.
Status: Reviewed
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0



Problem: Exporting Project Management / Project Manager project to P3 and activities with Remaining Duration = 1 come over with 0% and Remaining Duration = Original Duration.
Problem: When importing a P5 project into P3, remaining duration gets set to the original duration.
Problem: Percent complete coming into P3 as 0 when exporting from Project Management / Project Manager.
Problem: Activity percent complete changes when exporting from P6 and importing to P3.
Cause: If the activity’s RD = 1, this will occur.
Fix: This known problem in Project Management is currently under review and may be corrected in a future release.
Fix:

Workaround:



  1. In Project Management, create a User Defined Field (UDF) for those activities where Remaining Duration = 1, and Remaining Duration <> Original Duration.
     

  2. Export from Project Management.
     

  3. Import to P3.
     

  4. In P3, run a Global Change to correct the Remaining Duration (back to “1″) for the necessary activities.