Solution ID: prim14595 |
Apply Actuals does not update activities with actual units or duration |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
Fact: | Apply Actuals |
Problem: | Apply Actuals does not update activities with actual units or duration. |
Problem: | Apply Actuals just changes the data date and pushes out the activities. |
Cause: | The resources or activities are not set to Auto Compute Actuals. |
Fix: | To set Auto Compute Actuals on for a resource, follow the instructions below: 1. Go to the Resources screen by selecting Enterprise, Resources. To set Auto Compute Actuals on for an activity, follow the instructions below: 1. Go to the Activities screen by selecting Project, Activities. NOTE: Use the Fill Down feature to set this option for multiple activities. |