prim14595:Apply Actuals does not update activities with actual units or duration

$
0
0
Solution ID: prim14595
Apply Actuals does not update activities with actual units or duration
Status: Reviewed
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0

Fact: Apply Actuals
Problem: Apply Actuals does not update activities with actual units or duration.
Problem: Apply Actuals just changes the data date and pushes out the activities.
Cause: The resources or activities are not set to Auto Compute Actuals.
Fix: To set Auto Compute Actuals on for a resource, follow the instructions below:

1. Go to the Resources screen by selecting Enterprise, Resources.
2. Select the desired resource.
3. Click on the Details tab and check the box for Auto Compute Actuals.


To set Auto Compute Actuals on for an activity, follow the instructions below:


1. Go to the Activities screen by selecting Project, Activities.
2. Go to View, Columns. From the General section, select Auto Compute Actuals and add to the Selected Options. Click OK to add the column.
3. Check this column for any activities to auto compute.


NOTE:  Use the Fill Down feature to set this option for multiple activities.