prim14537:Why is CTD and CTC not calculating automatically after marking the activity to be 100 PCT complete?

$
0
0
Solution ID: prim14537
Why is CTD and CTC not calculating automatically after marking the activity to be 100 PCT complete?
Status: Reviewed
Version(s): 3.x

Problem: Why is CTD and CTC not calculating automatically after marking the activity to be 100 PCT complete?
Fix: 1 - Go to Tools, Options, Autocost Rules.

Under ’When quantities change use Current Unit prices to Recompute costs’ check Budget, Actual to Date, and Estimate to Complete


Also check Perform these calculations during each schedule computation.   Then go to Tools, Schedule.  Now your autocost rules will recalculate your costs.


2 – Make sure that the RPCT in the Resources window is Blank and not 0.0.  RPCT set to 0.0 is considered 0% and not blank. 



To re-set the RPCT value to blank use Sample Global Change: Deleting resource percent complete and resource duration