How do I show a roll up of duration in the grouping band?
Status: Reviewed
Version(s): 3.5, 3.5.1, 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0



Problem: How do I show a roll up of duration in the grouping band?
Fix: 1. Select Enterprise, User Defined Fields.

2. Create an activity level user defined field that is a ‘Number’ data type.  Then close the User Defined Fields dialog.



3. Back in the Activity View, select Tools, Global Change. 


4. Create a new global change and make the user defined field equal to the planned\original duration.



5. Run the global change, commit the changes, and exit the global change dialog.


6. Back in the activity view, add the new User Defined field as a column.  The values will roll up to the group band.