prim20722:Is it possible toformat a baron the Gantt Chartto highlightactivities whichspan a weekend?

$
0
0
Solution ID: prim20722
Is it possible to format a bar on the Gantt Chart to highlight activities which span a weekend?
Status: Reviewed
Version(s): 4.0, 4.1



Problem: Is it possible to format a bar on the Gantt Chart to highlight activities which span a weekend?
Fix: Workaround:

Part 1:  Run a Global Change to set a user defined field to the day of the week of the Start date of the activity






Part 2:  Create a bar whose Filter uses the user defined field which now contain’s the Start’s day of the week and the Original Duration to work out whether an activity will span a weekend.



 