Solution ID: prim19444 |
Early Finish date is before Early Start date. |
Status: Reviewed |
Version(s): 3.0, 3.0a, 3.0b, 3.0c |
From Primavera OCP
Problem: | Why is the Early Finish date before the Early Start date? |
Problem: | Early Finish date is before Early Start date. |
Cause: | Activity has duration = 0. |
Fix: | Non-milestone activities must have a positive duration. (minimum: 1 hr) Either: 1.) change the activity, with zero duration, to ‘Start milestone’ or ‘Finish milestone’ type NOTE: Please reference pages 67 –> 70 of the SureTrak User’s Guide: “Defining Activity Types” |