prim19440:How to deprogress a project in Project Management

$
0
0
Solution ID: prim19440
How to deprogress a project in Project Management
Status: Reviewed
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0



Problem: How to deprogress a schedule in P6.
Problem: How to deprogress a project in Project Management in versions 5.0 and P6.
Problem: How to unprogress a schedule.
Problem: How to unprogress a project.
Problem: How re-set a schedule with progress.
Problem: How re-set a project with progress.
Problem: How to create a new schedule from a project with actuals.
Problem: For started activities, how can I remove progress and return my activities to the original duration and budgeted units?
Problem: Global Change to completely remove % completes and actuals
Fix: Please perform the following steps to remove the progress from your project in the order that they appear in this list:

  1. Choose Enterprise, Projects and select the Calculations tab.   Choose to “Link Budget and At Completion for not started activities” and “Reset Remaining Duration and Units to Original

  2. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.

  3. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.

  4. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.

  5. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.

  6. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.

  7. Run the 2nd global change which sets the activity status to Not Started.


1st Global Change:


Subject Area:
Activity Resource Assignments


If:
Resource Type equals Material


Then:
Actual Material Units = 0




2nd Global Change:


Subject Area:
Activities


If:
Where Activity Status is not equal to Not Started


Then:
Activity Status equals Not Started




If this process is not used you may encounter the following error:


“Cannot set status to Not Started if activity has actuals.”


3rd Global Change:


Add duration to activities by running global change for Not Started activities


Subject Area:
Activities


If:
Where Activity Status is equal to Not Started


Then:


Remaining Duration = Original Duration