prim18231:Why does the entire Budgeted Cost spread only on the first day of the activity?

$
0
0
Solution ID: prim18231
Why does the entire Budgeted Cost spread only on the first day of the activity?
Status: Reviewed
Version(s): 3.x



Problem: Why does the entire Budgeted Cost spread only on the first day of the activity?
Fix: Go to the Resources window via Activity Form and make sure that the Resource Duration is not set to zero.  Remove the zero to make it blank and schedule the project.