prim17975:I want to change my Original Duration but it stays at zero.

$
0
0
Solution ID: prim17975
I want to change my Original Duration but it stays at zero.
Status: Reviewed
Version(s): 3.0, 3.0a, 3.0b, 3.0c



Problem: I want to change my Original Duration but it stays at zero.
Problem: Original Duration is zero and I cannot change it, it always reverts to zero.
Cause: There is an Expected Finish Constraint prior to the calculated Early Start of the Activity.

Fix: Remove the Expected Finish Constraint or move it later than the Activity Early Start.