prim37163:Relationship Lag is not exporting correctly or moved to another activity when exporting to MPP format

$
0
0
Solution ID: prim37163
Relationship Lag is not exporting correctly or moved to another activity when exporting to MPP format
Status: Reviewed
Version(s): 4.0, 4.1, 5.0



Problem: Relationship Lag is not exporting correctly to MPP format
Problem: Relationship lag moving to another activity
Problem: Project exported from Project Management has different lag when opened in Microsoft Projects
Problem: Relationship Lag is incorrect in Microsoft Project when viewing a project exported from Project Management 


Problem: Relationship lag is different than in Project Management when imported into Microsoft Project
Problem: Lag is incorrect
Problem: If multiple dependencies on a task, dependency lags may be incorrect or assigned to the wrong activity when exported to MPP
Fix: This known problem in Primavera Project Management will be corrected in a future release. 
Fix: Workaround:

Export using the MPX file format.  In the MPX format all durations are exported in hours.  Open the project in Microsoft Project, go to Tools, Macro, Macros and choose Format Duration, click Run



Select the Duration unit and click OK.