prim34103:Can the Update Progress function update Activity information only (not resource assignment data)?

$
0
0
Solution ID: prim34103
Can the Update Progress function update Activity information only (not resource assignment data)?
Status: Reviewed
Version(s): 5.0



Problem: Can the Update Progress function update Activity information only (not resource assignment data)?

For example:
When using Update Progress in conjunction with a timesheet system that records actual hours worked, Update Progress should only update activity information such as Started, Finished, Remaining Duration and % Complete.

Fix: This issue is an existing Enhancement Request.