Solution ID: prim33393 |
Material Resource Assignments Spread Incorrectly When Imported From MS Project |
Status: Reviewed |
Version(s): 4.0, 4.0, 4.1, 4.1, 5.0 |
From Primavera OCP
Problem: | Material Resource Assignments Spread Incorrectly When Imported From MS Project |
Problem: | Material Resource assignments in MS Project are being placed on the first hour of the activity when imported, or when brought in by Project Link: Spread in MS Project (100 units over 100 day activity duration): Spread in Primavera: |
Fix: | This known problem in Project Management has been corrected in version 5.0 Service Pack 3. To download the latest 5.0 Service Pack, see: Solution ID: prim29265 揥hat are the latest Service Packs for Primavera version 5.0??/A> |