prim33393:Material Resource Assignments Spread Incorrectly When Imported From MS Project

$
0
0
Solution ID: prim33393
Material Resource Assignments Spread Incorrectly When Imported From MS Project
Status: Reviewed
Version(s): 4.0, 4.0, 4.1, 4.1, 5.0



Problem: Material Resource Assignments Spread Incorrectly When Imported From MS Project
Problem:

Material Resource assignments in MS Project are being placed on the first hour of the activity when imported, or when brought in by Project Link:


Spread in MS Project (100 units over 100 day activity duration):


 


Spread in Primavera:


Fix: This known problem in Project Management has been corrected in version 5.0 Service Pack 3.  To download the latest 5.0 Service Pack, see:

Solution ID: prim29265 揥hat are the latest Service Packs for Primavera version 5.0??/A>