Solution ID: prim33093 |
Can risks be used to impact schedule dates without changing resource information? |
Status: Reviewed |
Version(s): 4.1, 5.0 |
From Primavera OCP
Problem: | Can risks be used to impact schedule dates without changing resource information? |
Fix: | This cannot be done directly. Risks were not designed to impact activity dates directly. Workaround:
This could be used to create a delay in the schedule in the impact report |
Fix: | This issue is an existing Enhancement Request. |