prim33093:Can risks be used to impact schedule dates without changing resource information?

$
0
0
Solution ID: prim33093
Can risks be used to impact schedule dates without changing resource information?
Status: Reviewed
Version(s): 4.1, 5.0



Problem: Can risks be used to impact schedule dates without changing resource information?
Fix: This cannot be done directly.  Risks were not designed to impact activity dates directly. 

Workaround:



  1. Create a fake resource and assign it to the activity.  Make sure that the Duration type is set to Fixed Units/Time.

  2. Create the risk for that resource and have the labor units get impacted with an increase.

This could be used to create a delay in the schedule in the impact report

Fix: This issue is an existing Enhancement Request.