Solution ID: prim21309 |
Troubleshooting inaccurate totals in the Resource Table. |
Status: Reviewed |
Version(s): 3.0, 3.0a, 3.0b, 3.0c |
From Primavera OCP
Problem: | Troubleshooting inaccurate totals in the Resource Table. |
Problem: | Totals in the resource table appear incorrect. |
Fix: |
NOTE: The most common mistake is made when resources are assigned and the budgeted cost or budgeted quantity are manually populated.
|
Fix: | SureTrak divides the total resource cost by the duration (in days). Therefore totals in the resource table/profile are reflecting the cost per day, multiplied by the number of days in that time intervale (ie: week/month/quarter/year). |