Solution ID: prim19089 |
Resource actual finish is past the data date when activity actual finish is before data date. |
Status: Reviewed |
Version(s): 3.x |
From Primavera OCP
Problem: | Resource actual finish is past the data date when activity actual finish is before data date. |
Fix: | Check the duration on the resource assignment. Remove the resource duration to get the resource actual finish the same as the activity actual finish. |