Solution ID: prim18562 |
How to update an activity remaining duration and set the activity to Started via the Activity.xls macro |
Status: Reviewed |
Version(s): 5.0, 6.0, 6.1, 6.2, 6.2.1 |
From Primavera OCP
Problem: | How to update an activity remaining duration and set the activity to Started via the Activity4x.xls macro |
Problem: | How to update an activity remaining duration and set the activity to Started via the Activity5x.xls macro |
Problem: | How to update an activity remaining duration and set the activity to Started via the Activity6x.xls macro |
Fix: | 1. Use the ‘Get Activity Details’ command from the Login screen. 2. Set the status of the activity to TK_Active and then use the ‘Set Activity Details’ command from the Login screen to set the activity as started. 3. Run the ‘Get Activity Details’ command from the Login screen, edit the remaining duration, and then use the ‘Set Activity Details’ command from the Login screen. |