Solution ID: prim35271 |
How does Project Management perform Levelling? |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 |
Problem: | How does Project Management perform Resource Levelling? | ||||||||||
Problem: | Resource Levelling FAQs | ||||||||||
Problem: | Leveling FAQ | ||||||||||
Fix: | Question 1: What is Resource Levelling and what does it do? Answer 1: Resource Levelling is a process which helps to ensure that sufficient resources are available to perform the activities in your project, according to the plan. Resource Levelling works by moving an activity to a time when it’s resources are all available to work on the activity and as such can push out the end date of your project. Resource Levelling can be performed against any resource, regardless of the Resource Type (Labour, Non Labour and Material resources can all be leveled). To perform Resource Levelling on a project, go to Tools, Level Resources. |
||||||||||
Fix: | Question 2: How can Resource Levelling be removed? Answer 2: Scheduling the project (without Levelling it) will remove any changes to dates that were made by Levelling the project. |
||||||||||
Fix: | Question 3: How does the Leveler decide the order in which activities will be leveled? Answer 3: Activities enter the Leveler one at a time. The order in which activities enter the Leveler is decided as follows:
|
||||||||||
Fix: | Question 4: How does the software determine whether there are enough resources to allocate? Answer 4: Once an activity enters the leveler, it’s resource assignment’s Remaining Units/Time is compared with the relevant resource’s Maximum Units/Time (less any hours already used by other leveled activities on that date) for each day the activity is due to work.
Example: A program has three activities, which enter the leveler in the order A, B, C. All three activities have the same resource assigned whose Maximum Units/Time is 8h/d. None of the activities have any predecessors and without Levelling all three would therefore start on the data date (day 1) Activity A needs its resource for 6h/d across 3 days. Step 1. Activity A enters the leveler: Activity A’s Remaining Units/Time (6h/d) is less than the Resource’s Maximum Units/Time on days 1, 2 and 3. Step 2. Activity B enters the leveler: Activity A has already been leveled so the Resource only has 2h/d remaining on days 1, 2 and 3.
Activities A and B have already been leveled so the Resource only has 2h/d remaining on days 1, 2 and 3 and 4h/d remaining on days 4 and 5. |
||||||||||
Fix: | Question 5: How do constraints affect Levelling? Answer 5: All constraints are honoured during Levelling except As Late As Possible and Expected Finish constraints which are ignored during Levelling (i.e. Activities with only As Late As Possible and/or Expected Finish constraints will be leveled in order of their relationships and Levelling priorities, regardless of their constraint)
|
||||||||||
Fix: | Question 6: How does the Resource Levelling setting “Consider assignments in other projects with priority equal/higher than…” setting affect Levelling? Answer 6: Resource assignments in closed, summarized projects which have an equal or higher Levelling priority (where 1 is the highest possible Levelling priority, 100 the lowest) to the project being leveled will be considered ahead of the resource assignments in the project being leveled. If two or more projects are open, their activities will be considered equally, as though they were all part of the same project. Example 1: Project A has a Levelling priority of 20, Project B has a Levelling priority of 10, both projects are open, “Consider assignments in other projects with a priority equal/higher than…” is switched on and set to 15. Because both projects are open, the “Consider assignments in other projects with a priority equal/higher than…” setting is ignored and both projects activities are considered for Levelling as though they were in the same project.
Fig 1: Projects A and B, scheduled, but not levelled: Fig 2: Both projects are summarized, Project A is opened and then levelled: |
||||||||||
Fix: | Question 7: What does the setting to Preserve Early And Late Dates do and how does this affect activities dates when they are Levelled? Answer 7: This option allows the scheduled early and late dates to be retained in the Early Start and Early Finish fields and shows the Levelled dates in the Remaining Early Start and Remaining Early Finish fields. The Remaining late dates are the Scheduled rather than the Levelled late dates. The Levelled float is stored in the Remaining Float field. If this option is switched off then a backwards-pass of Levelling is also performed, meaning that the late dates may be moved earlier if over-allocation has occurred or if a successor has been delayed. The differences between the Levelling Forward and Backward passes are detailed below:
|
||||||||||
Fix: | Question 8: How does the option “Level resources only within activity Total Float” affect Levelling? Answer 8: This is a useful option to use if your time deadline is more important than your resource deadline because it allows you to choose to over-allocate resources. This option will not create negative float when Levelling and can only be used if Preserve Early and Late Dates is switched on. If Level Resources Only Within Activity Total Float is used, the process of deciding when an activity can happen is as follows:
|
||||||||||
Fix: | Question 9: What happens if the Resource never has enough time each day to work on the activity? Answer 9: The activity will be placed on its early dates and the Scheduling / Levelling log will show that the activity could not be Levelled |
||||||||||
Fix: | Question 10: How does activity type affect resource assignment Levelling? Answer 10: The following rules apply to Levelling resources:
|
||||||||||
Fix: | Question 11: Is there a flow-chart which shows the entire Levelling process? Answer 11: Yes, the flow-chart can be downloaded here: Resource Levelling Flow Chart.pdf (8kb) |