prim32367:Sample Global Change to make Actual Start/Finish dates equal Planned Start/Finish dates

Solution ID: prim32367
Sample Global Change to make Actual Start/Finish dates equal Planned Start/Finish dates
Status: Reviewed
Version(s): 3.5.1, 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1



Problem: Sample Global Change to make Actual Start/Finish dates equal Planned Start/Finish dates
Fix:

Image may be NSFW.
Clik here to view.


All of the following:
Then
Actual Start = Planned Start
and
Actual Finish = Planned Finish


Note:  This Global Change is designed to make all Activity Actual Dates = to the Activity Planned Dates.\


*This will make your Original Duration = Actual Duration if the activities have an Actual Start

Fix: View the Global Change Report to identify all affected activities.  Committing changes cannot be undone. 