Solution ID: prim32367 |
Sample Global Change to make Actual Start/Finish dates equal Planned Start/Finish dates |
Status: Reviewed |
Version(s): 3.5.1, 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1 |
From Primavera OCP
Problem: | Sample Global Change to make Actual Start/Finish dates equal Planned Start/Finish dates |
Fix: |
All of the following: Note: This Global Change is designed to make all Activity Actual Dates = to the Activity Planned Dates.\ *This will make your Original Duration = Actual Duration if the activities have an Actual Start |
Fix: | View the Global Change Report to identify all affected activities. Committing changes cannot be undone. |