prim30239:How is Earned Value Labor Units Calculated

$
0
0
Solution ID: prim30239
How is Earned Value Labor Units Calculated
Status: Reviewed
Version(s): 5.0



Problem: How is Earned Value Labor Units Calculated
Fix: Earned Value Labor Units – Earned Value Labor Units is the portion of the BL Labor Units that is actually completed as of the project data date. Computed as BL Labor Units * Performance % Complete.  The Earned Value Labor Units is essentially the labor units earned value for the activity. The method for computing the Performance % Complete depends on the earned value technique selected for the activity’s WBS.  The BL Labor Units is taken from the primary baseline.

Planned Value Labor Units Scheduled is the portion of the BL Labor Units that is scheduled to be completed as of the project data date.  Computed as BL Labor Units * Schedule % Complete.  The Schedule % Complete specifies how much of the activity’s baseline duration has been completed so far.  The BL Labor Units is taken from the primary baseline.


Viewing all articles
Browse latest Browse all 83

Trending Articles