prim30051:Export Activity Relationshipsto Excel, when Regional Settings are set tosome European countries, causes Lag to be multiplied by 100.

$
0
0
Solution ID: prim30051
Export Activity Relationships to Excel, when Regional Settings are set to some European countries, causes Lag to be multiplied by 100.
Status: Reviewed
Version(s): 5.0



Problem: Export Activity Relationships to Excel, when Regional Settings are set to some European countries, causes Lag to be multiplied by 100.
Problem: Duration is multiplied by 100 after exporting to Excel when using non-English regional settings
Fix: This known problem in Project Management has been corrected in version 5.0 Service Pack 2.

To download the latest Service Pack, see: Solution ID: prim29265 揥hat are the latest Service Packs for Primavera version 5.0??/A>

Fix: Workaround:

In Windows’ Regional Settings, change the decimal symbol to a dot (full stop or period) and the grouping symbol to a comma.


In Windows 2000, this can be achieved as follows:



  1. Start, Settings, Control Panel

  2. Double click Regional Options

  3. Switch to the Numbers tab

  4. Change “Decimal symbol” to “.”

  5. Change “Digit grouping symbol” to “,”

  6. Click OK


In Windows XP, this can be achieved as follows:



  1. Start, Control Panel

  2. Double click Regional and Language Options

  3. On the Regional Options tab, click “Customize”

  4. Change “Decimal symbol” to “.”

  5. Change “Digit grouping symbol” to “,”

  6. Click OK

 