prim14008:How is the Variance Finish date calculated?

$
0
0
Solution ID: prim14008
How is the Variance Finish date calculated?
Status: Reviewed
Version(s): 3.x, 4.0, 4.0, 4.1, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0

Problem: How is Variance Finish calculated?
Fix:

A Variance Finish date is calculated as BL Finish – Finish. 


If no baseline is defined, the current project is used as the primary baseline.


See also, Can Project Management select which dates to use when comparing baseline variances 

Fix: At the summary level, the Variance Finish date is calculated as the latest finish date – the latest baseline finish date.  The duration is then based of the global default calendar.
Fix: If the activity is a start milestone, then it will set the variance equal to the calculated Variance Start value.