Quantcast
Channel: Primavera Online Interaction » Activity Duration
Viewing all articles
Browse latest Browse all 83

prim17607:Global Change treating OD and RD as days instead of hours

$
0
0
Solution ID: prim17607
Global Change treating OD and RD as days instead of hours
Status: Reviewed
Version(s): 4.1



Problem: Global Change treating Original Duration and Remaining Duration as days instead of hours.

For example:


The following activity has a 5 day duration. At 8 hours per day, this is 40h.



 Use the following Global Change to set user defined finish dates equal to the Early Start plus the Original Duration and Remaining Duration:



 With a 5d (40 hour) duration, the user defined fields should be set to 07JAN.  However, Project Manager will treat the ‘hour value’ as the duration in days, pushing the user defined finish dates to 40 days after the start date.


Fix: This known problem in Project Manager will be corrected in a future release.

Workaround:
Using Global Change, divide the user defined duration by the hours per day.


Viewing all articles
Browse latest Browse all 83

Trending Articles