Solution ID: prim17607 |
Global Change treating OD and RD as days instead of hours |
Status: Reviewed |
Version(s): 4.1 |
From Primavera OCP
Problem: | Global Change treating Original Duration and Remaining Duration as days instead of hours. For example: The following activity has a 5 day duration. At 8 hours per day, this is 40h. Use the following Global Change to set user defined finish dates equal to the Early Start plus the Original Duration and Remaining Duration: With a 5d (40 hour) duration, the user defined fields should be set to 07JAN. However, Project Manager will treat the ‘hour value’ as the duration in days, pushing the user defined finish dates to 40 days after the start date. |
Fix: | This known problem in Project Manager will be corrected in a future release. Workaround: |