Problem: | Can Suretrak schedule in weeks? |
Problem: | How to view activity durations in ‘weeks’? |
Fix: | There is no direct way to make suretrak schedule in weeks. However the display style can be set to week, day by going to tools-> options and when activity duration is entered, follow it by a w such as 3w. This will give the activity a duration of three weeks. |