Solution ID: prim16876 |
What does "Recalculate schedule dates according to modified workweek" mean? |
Status: Reviewed |
Version(s): 3.0, 3.0a, 3.0b, 3.0c |
From Primavera OCP
Problem: | User changes a calendar’s workweek and is prompted to recalculate schedule dates according to modified workweek. How is SureTrak recalculating dates or durations? |
Problem: | What does “Recalculate schedule dates according to modified workweek” do? |
Problem: | Activity duration or dates change after modifying its calendar workweek |
Fix: | When changes are made to calendars, SureTrak asks: “Recalculate schedule dates according to modified workweek?”
|
Fix: | For an explanation of calendar calculations and using multiple base calendars, that have different durations than the global calendar, see solution 200192114301. |