prim16876:What does “Recalculate schedule dates according to modified workweek” mean?

$
0
0
Solution ID: prim16876
What does "Recalculate schedule dates according to modified workweek" mean?
Status: Reviewed
Version(s): 3.0, 3.0a, 3.0b, 3.0c



Problem: User changes a calendar’s workweek and is prompted to recalculate schedule dates according to modified workweek.  How is SureTrak recalculating dates or durations?
Problem: What does “Recalculate schedule dates according to modified workweek” do?
Problem: Activity duration or dates change after modifying its calendar workweek
Fix:

When changes are made to calendars, SureTrak asks: “Recalculate schedule dates according to modified workweek?”




    • If Yes is clicked, the activities duration (in total hours) is maintained while the dates will be recalculated according to the new calendar.
    • If No is clicked, the activities dates AND times will be maintained while the duration will be recalculated to reflect the new number of hours worked per day.
    Fix: For an explanation of calendar calculations and using multiple base calendars, that have different durations than the global calendar, see solution 200192114301.